Wednesday, June 13, 2007

Irritated Gaulbladder

Final acceptance

Today came by our construction manager to go through with us the loss of the house. We have defined a list of 14 outstanding points. One was the re-introduction of the concrete in the basement stairwell (in this case the insulation was not executed properly), and a few small things for FINGER HOUSE. Most points, however, had the heating company in the neck, while you had already done the day before yesterday can ...

Mr. Weber, our construction manager, handed us a gift for the collection, which kept us very happy.

At this point I would like to express another special praise to our excellent site managers, who make from early morning until late at night with our questions and problems and had always had a response or solution at hand. As I have already heard of supervisors of a difference.

Keep it up!

Tuesday, June 12, 2007

Funeral Flower And Suggested Words

final assembly

Today came the carpenter from FINGER house for final assembly. They built the doors, took out the stairs, stopped the windows and installed the extensions of the gutter. You also gave us a few tips for laminate laying.

As I feared, you do not Heizkreisabdeckungen mounted. They told us that it makes the heating company. Quite clearly on the covers even stood on it, who you ordered: the heating company!

Monday, June 11, 2007

How To Delete Your Sorority Life Character

What makes since only the heating company

Today was the heating company there. They were busy with the loading and Ventilation system employed, the points which we had objected to the last conversation with the supervisor, were not removed from you. For the heating we were told that the outside temperature sensor is disconnected and thus would not appear to be no need for action. I asked if he would also have tested electrically, which he declined to confirm not. A view to a later period of the day on the remote control but showed at an outside temperature of 0 C. A little cold for the season or does it still disconnect?

Furthermore we had to discuss the installation of the covers of the heating circuit. Lt. our knowledge, it should mount the heating company this in turn claimed that it makes FINGER. We'll see what happens.

Sunday, June 3, 2007

Gold Tinged Cervical Mucus

We are making good progress!

The last day was announced a lot of work in the house: we have heat insulating screed published in the utility room and completes the electrical system on. In addition, the first holes of the basement ceiling was - one of the few benefits the clients will always stick to the builders - closed.

for painting and tiles, we have instructed our experts on MyHammer. We are quite surprised how well and how quickly the work go forward.

This week is yet to pass the heating company, einzujustieren to the heating and in a briefing for heating and Ventilation system. Also still have some minor deficiencies are corrected.

Friday, May 25, 2007

What Does A Pinky Ring Mean

Help! A software error in the pellet!

Now that we have finished the heating program for the screed, we wonder why the heating is every 5 hours in to burnout, and then the burner restart. With this problem we seem to not be alone: a brief search on Google promotes interesting information to light:

When installed VIESSMANN Vitolig 300 type VL3A - identical to the way the wind Hager BioTherm - the burner off after a negative boiler setpoint jump of> 10 K permanently stored. Thus, after a hot water heating, the storage set value + = 30K is boiler set point, a burner shutdown Take place if at the same low set point requirements (+ differential temperature) pending the heating circuits.
The setpoint increase (+30 K) for water heating is also permanent and can not be parameterized.
results basically fixed target "burners with Setpoint Change> 10 K" from the request to the overheating of the boiler. should be prevented by turning off the burner, the boiler temperature to the safety temperature (95 ° C Safety) increases. Especially after the hot water then with little loss, ie little circulation in the boiler can be a strong rise in temperature, but the burner is on low load. Even after the The burner is discharged into the Ausbrandphase still for several minutes heat to the boiler. These requirements are permanently stored in the boiler control and are not performance-based differentiated not adjustable, which here would be required.

Now, in the Vitolig 300 with only 10 kW that argument difficult to understand because the Nachheizleistung is relatively low in the Ausbrandphase.

I'm going to involve the heating company, because this problem should be well resolved in software versions> 2.10. Of course, we have version 2.10, how could it be otherwise?

Donde Encontrar Trasvetis Chicago Illinois

House Tour

finger house plans on 9.6. and 10.6. a typical walk in our 200th Medley More information is listed under http://www.fingerhaus.de/fingerhaus/index.php?parent=2360 .

As a tip for the journey: the address is located in the western outskirts of the village development area. It is best achieved if the destination address "deer highway 71" in the navigation device types. The house is only 100 m away and the brown roof easy to spot.

Thursday, May 24, 2007

Hindware Sanitary Ware

finished installing electric blower door

was now completed the electrical installation. I've honestly do not understand why we must now have had to make the covers on the outlets and switches. On Saturday comes the painter, who must now remove the covers.

The argument was that we certainly all Covers replaced. Why the pre-installation does not simply with the final installation of interior doors, this does not explain, however.

The problem with the wall too close to the subsequent coverage in the study has not been solved yet.

Sebaceous Warts Epsom Salt



On Tuesday, the blower door test was conducted. The value of n50 was looked after with finger house <1,0 festgelegt. Erreicht haben wir 1,2. Dieser war auf Undichtigkeiten im Bad, am Kamin, den Wasserleitungen in der Küche und der noch nicht justierten Terassentür zurückzuführen.

Our construction manager is just around the difficulties. An additional test will be done but probably only after the final assembly.

Monday, May 14, 2007

Cheap Jigsaw Puzzle Frames

exterior plaster started

Tonight I was to air on the site. Since even the plasterers were at work. The front of the house was already finished tonight.

Slowly but the garbage piles up on the site. Where was there but the same container that was in the construction work description?

Sunday, May 13, 2007

University Of Houston

insulation incomplete

This weekend we have the insulation measures and the filling work closer look. In Kellervorraum the walls must wg. KfW40 be insulated both on the hot side and on the cold side to the heated room out. It should be noticed that the wall was not insulated in the boiler room on the cold side. If this wall password?

No wonder: this is the wall filled pellet silo, which weighs about 3 tons. I'm curious to see how finger house will solve this problem. Tomorrow I shall in the early call the site manager.

Kosher Ginger Cookies

Where is SAT1 and PRO7 gone?

After next week the scaffolding is removed, it was time to align the satellite dish. Equipped with Receiver and multi-switch, I went with a friend who has the climbing experience, to work. This

have found out our brick during the ascent as almost insurmountable obstacle. Even with climbing shoes Christian is just slipped. Only when he is barefoot again tried worked there.

When we had successfully aligned the antenna, the researchers were asked where are the 1,200 digital channels, then, Pro7 and Sat1 gone? There was a lot of Arab Sexkanäle.

The standard programs were not easy to locate, so I put the Receiver back to the factory. As it turned out that we had the wrong satellite in sight: it was instead Hotbird Astra. So once again all over again and see there ...

Wednesday, May 9, 2007

Katesplayground Blue Ray

filling work almost done

I was here after two days of absence due to a business trip back to the site. Meanwhile, had already done a lot, because the walls had all been smoothed.

One or the other has now revealed: a basement window does not open completely, because the pipes of the ventilation system in the way of a door in the conservatory could be after not re-open . Close When our brick is on it will completely still an open point.

morning passes by the heating company so that we can discuss the heating program. When the pellet is manually ie we increase the temperature daily at a piece and by hand.